EITG CALENDAR & ANNUAL TIMELINE

Enterprise IT Governance (EITG) Calendar & Timeline

Timeline

The annual timeline for EITG is described below

down arrow

Project Intake 

 June – *January 15 

  • Gathers project intake requirements 
  • Obtains department leader support, approval, and sponsorship 
  • Engages and completes Purchasing Department Request For Information/Proposal (RFP) process (if required) 
  • Project Requestor send completed intake form to EITG@spps.org 

 

Note: *January 15th deadline for next year's budget; however, proposals accepted all year

down arrow Ongoing
(January – December) 

  • Acknowledgement sent to Project Requestor their request received includes with overview of the EITG process 
  • Record Project Intake Form 
  • Intake form confidentially shared with Change Advisory Committee for review 
  • Project intake Q &A scheduled with Requestor, Change Advisory Committee, and If required, technical resource(s) 

down arrow

Bi-weekly/as needed 

  • Q & A session with Project Requestor 
  • Evaluation performed 
  • Existing solution(s) and/or process 
  • Requirements clearly defined 
  • District Strategic Alignment 
  • District impact 
  • District value 
  • Technical standards 
  • Service ownership and responsibilities identified 

 

Note:  Assessment, scoring, and status assignment performed next committee meeting if evaluation complete. 

down arrow

  • Obtains high-level ETCs (Estimated Time to Complete) effort hours from Technology Services within 1-2 weeks 
  • Project Proposal(s) 40 hours or less sent through Service Desk request system (Project Requestor and Leader informed) 

 

down arrow

 

 

  • Project Proposal(s) scoring 
  • Project Proposal(s) assigned status of Declined, Future Consideration, or SELT (Senior Executive Leadership Team) Consideration 

down arrow

 

 

  • Update Project Proposal Record with Change Advisory Committee evaluation results 
  • Schedules Enterprise Governance Committee presentation(s) 
  • Sends presentation guidelines and schedule to Project Requestor and Department Leader 

down arrow

March 

  • Project Presentations 
  • Final review/evaluation of projects   
  • Projects authorized or declined   
  • Project Prioritization  
  • Project Planning  

down arrow

July 

  • Project Kickoffs 

Calendar

The Change Advisory Committee accepts Requests throughout the year at its monthly meetings. They will score requests on a rubric and then submit reviewed projects to the Senior Executive Leadership Team (SELT) in March. At that time, more information will be provided on the calendar as projects move forward. 